How to write a change order that gets paid
Most payment disputes on small construction jobs start with work that changed without paperwork. The owner asks for an extra outlet, the inspector wants a different header, the tile the owner picked is back-ordered, and three weeks later nobody agrees on what was approved or what it costs. A written change order, signed before the changed work starts, settles those questions while everyone still remembers the conversation. This guide shows what to put in one, how to price it, and the habits that get change orders paid.
What a change order is
A change order is a short written amendment to your contract. It describes work that is added, removed or changed, the price difference, any change to the schedule, and it is signed by the owner and the contractor. Once signed, it becomes part of the contract. Your original contract should say that changes must be in writing; the change order is how you follow that rule on every job.
What every change order should include
- Change order number and date, numbered in order (CO-01, CO-02...) so nothing gets lost.
- Project name, job address and original contract date, so it ties to the right contract.
- Who asked for the change and why: owner request, hidden condition found during work, inspector or code requirement, or a material substitution.
- A specific description of the work. "Add two 20-amp kitchen counter receptacles on the island, including wire, boxes and patching" is specific. "Electrical extras" is not.
- The price change, broken into labor, materials and other costs if your contract calls for it.
- The new contract total, with the running history (see the next section).
- The schedule change, in calendar days, even if it is zero.
- Payment terms for the change: paid with the next progress payment, or due before the work starts.
- Signatures and dates of the owner (or the owner's authorized agent) and the contractor.
Show the math every time
Owners sign faster when the numbers are visible and add up. Put this block on every change order:
| Line | Amount |
|---|---|
| Original contract sum | $48,500.00 |
| Net change from earlier change orders (CO-01, CO-02) | $1,850.00 |
| Contract sum before this change order | $50,350.00 |
| This change order (CO-03): add island receptacles | $640.00 |
| New contract sum | $50,990.00 |
| Schedule change | +1 calendar day |
A deduction works the same way with a negative number. If the owner drops the backsplash, show "-$1,200.00" and the lower new total. Credits build trust and keep the running total honest.
Three common kinds of change
Fixed-price change
You price the change before you start and the owner agrees to that number. Best for anything you can measure: extra square feet of tile, an added window, a larger water heater.
Time-and-materials change with a cap
When you cannot know the scope until you open the wall, such as rot behind siding or old wiring, agree on hourly labor rates, how materials are marked up, and a not-to-exceed amount. Stop and get a new signature before you pass the cap.
Allowances and selections
If the contract has an allowance (for example, a fixture allowance) and the owner picks something that costs more, the difference goes on a change order. If they pick something cheaper, credit the difference the same way.
Sign before you build
Make it a rule that no changed work starts without a signed change order. When the owner approves in person or by phone, send a written summary the same day (text or email: what, how much, how many days) and ask for a reply saying "approved." Then follow with the signed form. A written yes is far better than a remembered conversation, and the signed form is better still.
If the change comes from a hidden condition or a code requirement, stop that part of the work, photograph what you found, and write the change order before you cover anything up. Photos dated the day you found the problem make the price easy to accept.
Why change orders matter for getting paid
- Final payment. The signed change orders are the record of what the final contract sum is. Without them, the last invoice becomes a negotiation.
- Lender draws. On financed jobs, lenders often want signed change orders before they release money for extra work.
- Lien rights. In Florida, a claim of lien must state the labor, services or materials furnished and the contract price or value under section 713.08(1). Signed change orders are how you show the contract price after changes. Claim only what is actually unpaid.
Common mistakes
- Doing the work first and writing the change order at the end of the job
- Vague descriptions that the owner can read two ways
- Leaving out the schedule impact, then being blamed for the delay
- Letting someone other than the owner or the owner's authorized agent sign
- Bundling ten small changes into one surprise at the end
- Forgetting credits for work that was removed
A quick checklist before you send it
- ☐ Numbered, dated and tied to the right contract
- ☐ Description specific enough for a stranger to price
- ☐ Price, running total and new contract sum add up
- ☐ Schedule change stated, even if zero
- ☐ Payment terms for this change stated
- ☐ Photos attached for hidden conditions
- ☐ Signed by both sides before the work starts
Keep the trail
File each signed change order with the contract, in number order, with any photos and the written approvals. If a final payment or lien dispute comes up, that file is what you will rely on.
General information, not legal advice. FL Contract Forms is a private company, not a law firm. For a dispute on a specific job, talk to a Florida construction attorney.
The FL Contract Forms bundle includes an editable change order with these fields, the running-total block and signature lines already laid out.
Related: how to write a construction proposal. The FL Contract Forms bundle includes an editable change order form.
- section 713.08(1) (leg.state.fl.us)
Florida contractor contract templates with the required notices built in. See pricing