Florida Contractor Deposit Rules (s. 489.126)
Florida does not set a fixed percentage that a contractor may collect up front on a home job. What it does is attach deadlines to larger deposits. Under section 489.126 of the Florida Statutes, once an initial payment on residential work is more than 10 percent of the contract price, the contractor has firm duties about permits and starting the work, and missing them can become a crime. Here is what the statute says, as it reads in the 2026 Florida Statutes, and how to write a deposit into your contract so it holds up.
Is there a legal limit on deposits in Florida?
Section 489.126 does not cap the deposit. A contractor can ask for 10, 30 or 50 percent if the owner agrees. The 10 percent line matters because it switches on the duties below. The section covers anyone who performs or promises to perform contracting work, whether or not the person holds a license, and it applies to repair, restoration, improvement or construction of residential real property.
What applies when the deposit is more than 10 percent
A contractor who receives more than 10 percent of the contract price as an initial payment must:
- Apply for the permits the work needs within 30 days after the payment is made, unless the work needs no permit under the local codes, and
- Start the work within 90 days after all necessary permits are issued.
There are two ways out. The contractor may have just cause for the delay, or the owner may have agreed in writing to a longer period for the permit application, the start date or both. That written agreement is the reason a clear contract matters: a specific later date, signed by the owner, replaces the default clock.
The 90-day rule once work has started
The statute also covers jobs that stall. A contractor holding more money than the value of the work performed may not fail or refuse to perform any work for any 90-day period, or for a different period the contract specifies. Stopping is treated as evidence of a violation unless the stop was caused by the owner ending the contract or materially breaching it, or the contractor had just cause. A contractor who ends the job must send the owner a letter giving the reason, by certified mail, return receipt requested, to the owner's address in the contract.
The written demand letter
Before these rules are enforced, the owner sends a written demand. The letter asks the contractor to apply for the permits, start or resume the work, or refund the money, and it goes by certified mail, return receipt requested, to the contractor's address in the contract. If the contract lists no address, or there is no written contract, it goes to the address the contractor has on file for licensing. If the contractor does not act or refund within 30 days of receiving the demand, the law allows an inference that there was no just cause.
Penalties under section 489.126
The penalty depends on the amount involved:
- Less than $1,000: first-degree misdemeanor
- $1,000 to less than $20,000: third-degree felony
- $20,000 to less than $200,000: second-degree felony
- $200,000 or more: first-degree felony
For the permit and start-date rule, the amount is the total money received. For the 90-day rule, it is the money received in excess of the value of the work performed. The statute also says that intending to return the money later is not a defense.
A related rule: misapplication of construction funds
Section 713.345 adds a second duty. Anyone who receives a payment for improving real property must use it to pay what is then due to the workers and suppliers whose labor or materials went into the job before that payment came in, except amounts held back under the contract or in a good-faith dispute. Knowingly failing to do so is misapplication of construction funds, a felony at every amount. Paying another job's bills while this job's suppliers are still waiting is the classic way contractors end up here.
How to write the deposit into your contract
- State the deposit as a dollar amount and as a percentage of the contract price.
- If it is over 10 percent, include a clause that repeats the 30-day permit and 90-day start duties.
- If you need more time, for example for custom materials or a slow permit office, write the later dates into the contract and have the owner sign or initial them.
- Tie the remaining payments to milestones, such as permit issued, rough inspection passed and final inspection passed.
- Put your correct business address in the contract, since demand letters are sent there.
- Keep the permit application receipt and dated photos of the start of work.
A quick checklist for homeowners
- Ask for the permit application date and the start date in writing before paying a large deposit.
- Pay by check, card or bank transfer so there is a record.
- Keep a signed copy of the contract with the contractor's address on it.
- If the job does not start or stalls, send the written demand by certified mail and keep the receipt.
This guide is general information, not legal advice. For a specific dispute, talk to a Florida attorney.
The FL Contract Forms residential agreement already includes a section 489.126 deposit clause, a milestone payment table and a change order form you can edit in Word.
Related: how to write a construction proposal. The FL Contract Forms bundle includes an editable proposal template and the residential agreement with the Recovery Fund and lien law notices built in.
- section 489.126 (leg.state.fl.us)
- Section 713.345 (leg.state.fl.us)