Florida Chapter 558 defect notice: deadlines for contractors
Before a Florida property owner can sue a contractor over a construction defect, Chapter 558 of the Florida Statutes requires a written notice of claim and a chance for the contractor to inspect and offer a fix. For a contractor it is a short, fixed window to settle a complaint before it becomes a lawsuit. This guide follows sections 558.002, 558.004 and 558.005 as they read in the 2026 Florida Statutes.
What counts as a construction defect
Section 558.002 defines a construction defect as a deficiency in the design, specifications, surveying, planning, supervision or observation of construction, or in the construction, repair, alteration or remodeling of real property, that results from defective materials, products or components; a building code violation; a design that failed the professional standard of care when it was approved; or work that fails accepted trade standards for good and workmanlike construction. It covers contractors, subcontractors, suppliers and design professionals, and claims by owners, later buyers and associations.
The notice of claim
The claimant must serve the written notice at least 60 days before filing suit, or at least 120 days when the action involves an association representing more than 20 parcels. The notice must refer to Chapter 558, describe each alleged defect in reasonable detail along with the resulting damage if known, and, based on at least a visual inspection, identify the location of each defect well enough for the people served to find it. When the claim comes from a contract, it goes to the person the claimant contracted with. Service means certified mail with a delivery record, hand delivery, or courier delivery with written proof.
The contractor's deadlines
| Step | Individual owner | Association (more than 20 parcels) |
|---|---|---|
| Inspect the property | Within 30 days after service | Within 50 days |
| Forward the notice to subcontractors, suppliers or design professionals | Within 10 days after service | Within 30 days |
| Their written response to you | Within 15 days after you forward it | Within 30 days |
| Your written response to the claimant | Within 45 days after service | Within 75 days |
The inspection happens at a time agreed with the owner, during normal working hours, and destructive testing is allowed only if both sides agree. When you forward the notice, name the specific defect you believe each recipient is responsible for; forwarding is not an admission of anything. Once you make an offer, the claimant has 45 days to accept or reject it in writing.
What your response can say
Section 558.004(5) lists five kinds of written response:
- An offer to repair the defect at no cost to the claimant, with a detailed description of the repair and a timetable.
- An offer to settle with a payment of money, with a timetable. This offer does not obligate your insurer.
- An offer combining repairs and a payment.
- A statement that you dispute the claim and will not repair or pay.
- A statement that your insurer will decide on a monetary payment within 30 days.
If you dispute the claim or miss the deadline
If you dispute the claim, or do not respond in time, the claimant may file suit without any further notice. If the claimant accepts your offer and you then fail to make the repair or the payment on schedule, the claimant may also sue. Serving the notice tolls the statute of limitations for everyone covered by the chapter until the later of 90 days after service (120 days for an association) or 30 days after the repair or payment period in an accepted offer ends.
Either side can request documents
Under section 558.004(15), either party may make a written request, citing that subsection, for relevant records such as plans, specifications and as-built drawings, photos and videos of the defect, expert reports, subcontracts, purchase orders and maintenance records. They are exchanged within 30 days, and the requester offers to pay the cost of copies.
The notice your contract must contain
Section 558.005(6) says a written contract for improvement of real property between an owner and a contractor or design professional, entered into after October 1, 2009, must contain a notice substantially in this form:
ANY CLAIMS FOR CONSTRUCTION DEFECTS ARE SUBJECT TO THE NOTICE AND CURE PROVISIONS OF CHAPTER 558, FLORIDA STATUTES.
The statute names no penalty for leaving it out, and the chapter applies anyway unless the parties agree in writing to opt out. It still helps: the owner learns from day one that a defect complaint starts with written notice and a chance to fix it.
Practical steps when a notice arrives
- Write down the date of service and put the day-30 and day-45 deadlines (50 and 75 for associations) on your calendar.
- Read your liability policy's notice requirements and tell your insurer promptly.
- Confirm the inspection date in writing, and take dated photos and notes during the visit.
- Forward the notice within 10 days to any subcontractor or supplier whose work is involved.
- Send a written response that fits one of the five options before day 45, and keep proof of delivery.
Sources
- Florida Statutes (2026), section 558.002, definitions
- Florida Statutes (2026), section 558.004, notice and opportunity to repair
- Florida Statutes (2026), section 558.005, contract provisions and application
This guide is general information, not legal advice. For a specific claim, talk to a Florida construction attorney.
The FL Contract Forms residential agreement includes the Chapter 558 contract notice, the Recovery Fund notice and the lien law disclosure page, ready to edit in Word.
Related: required notices in a Florida residential contract. The FL Contract Forms bundle includes the residential agreement with the Recovery Fund and lien law notices built in.